Paving on Greenville Rd & Jackson Rd to begin in September

9/7/22 Update - Due to the recent rain, paving will now begin on Monday September 12th
------------------------------------------
Our work on Greenville Road will take another step forward on Thursday September 8th when the road will be fine graded to its finished form before paving. It will be shaped and compacted and by Friday afternoon will be ready. On Saturday September 10th the paving crew will take over and layout approximately 1,050 tons of asphalt and roll it smooth. The road will be open during these 3 days but there will be delays. We recommend avoiding the area if possible. If you do need to go thru watch for our flagger's and wait for their signal that it is safe to go thru.

Other work coming up on September 16th and the 20th is paving the first steep hill on Jackson Road from route 123. This will keep the gravel from washing out during heavy rains. Again, if you can avoid this area on those days we would appreciate it. Thank you. (Mason Highway Department)